NIMS defines three EOC activation levels: Level 3, Normal Operations/Steady State; Level 2, Enhanced Steady-State/Partial Activation; and Level 1, Full Activation. NIMS asks jurisdictions to use the standard titles when communicating outside their organization and, if they use numbers, to count down so that Level 1 is full activation.
The NIMS activation levels
Table 2 of the National Incident Management System (third edition, October 2017) sets out the levels:
| Level | NIMS title | Description |
|---|---|---|
| 3 | Normal Operations / Steady State | Activities that are normal for the EOC when no incident or specific risk or hazard has been identified. Routine watch and warning activities, if the EOC normally houses that function. |
| 2 | Enhanced Steady-State / Partial Activation | Certain EOC team members or organizations are activated to monitor a credible threat, risk or hazard, and/or to support the response to a new and potentially evolving incident. |
| 1 | Full Activation | The EOC team is activated, including personnel from all assisting agencies, to support the response to a major incident or credible threat. |
NIMS adds that any of these levels can involve both in-person and off-site personnel coordinating virtually.
Why EOC level numbers differ between jurisdictions
NIMS is explicit: EOC personnel should use the standard activation titles (Normal Operations, Partial Activation, Full Activation) when communicating outside their jurisdiction or organization. Organizations may use numbers or colors internally. When numbers are used, NIMS says they "should reflect the standard NIMS approach of descending numbers meaning higher levels of activation (e.g., full activation should be level 1)."
In practice, numbering has varied. Some jurisdictions historically counted up, with the highest number meaning full activation. Others use four or more levels, or add a monitoring stage before activation. Washington State, for example, reversed its numbering so that its highest activation level became Level 1. When you coordinate with another EOC, use the titles rather than the numbers, or confirm what their numbers mean.
What typically changes at each level
NIMS defines the levels by purpose. Staffing and actions at each level come from the jurisdiction's emergency operations plan. A common pattern:
| Level 3: Steady state | Level 2: Partial | Level 1: Full | |
|---|---|---|---|
| Who is in the EOC | Emergency management staff, duty officer | Selected sections or agency representatives for the threat at hand | All sections and assisting agencies |
| Typical work | Monitoring, watch and warning, plans, training and exercises, facility readiness | Situational awareness, targeted coordination, resource tracking, public information | Full coordination of information, resources, plans and policy direction |
| Operational periods | Normal business hours | Extended or defined periods as needed | Defined operational periods, often around the clock |
| Documentation | Routine logs | Activity logs, situation reports | Full documentation: activity logs, situation reports, resource tracking, cost records |
What triggers activation
NIMS lists circumstances that might trigger EOC activation:
- More than one jurisdiction becomes involved in an incident, and/or the incident involves multiple agencies.
- The Incident Commander or Unified Command indicates the incident could expand rapidly, involve cascading effects or need more resources.
- A similar incident in the past led to EOC activation.
- The EOC director or an appointed or elected official directs activation.
- An incident is imminent, such as hurricane warnings, slow river flooding, predicted hazardous weather or elevated threat levels.
- Threshold events described in the emergency operations plan occur.
- Significant impacts to the population are anticipated.
Write your own triggers into the emergency operations plan, with the level each one calls for and who is notified.
Deactivation
Under NIMS, the EOC director deactivates staff as circumstances allow, and the EOC returns to normal operations. Deactivation typically happens when the incident no longer needs the EOC's support and coordination functions, or when individual organizations or steady-state mechanisms can manage those functions. Deactivation may be phased. Staff complete resource demobilization and hand over ongoing incident support or recovery activities.
Deactivation is also when documentation is easiest to lose. Collect activity logs, resource records and cost records before staff demobilize, because they feed the after-action report and any later Public Assistance claim.
Writing activation levels into your plan
- Use the NIMS titles. Adopt Normal Operations, Partial Activation and Full Activation as the official names, with numbers descending if you use them.
- Define triggers per level. Tie each level to concrete thresholds for your hazards, such as a flood stage or a warning type.
- List staffing per level. Name the sections, positions and agency representatives each level brings in, including virtual participation.
- Set notification paths. State who authorizes each level and how staff, partners and the state are notified.
- Exercise it. Test activation and deactivation in exercises, and capture lessons in an after-action report.
A step-by-step EOC activation checklist is available as a starting point.
How Elarchon helps
Elarchon gives the EOC the same record the departments work from: live command dashboards, damage assessment, mutual aid hours, public alerts and FEMA Public Assistance documentation. Activating to Level 2 or Level 1 does not mean starting a new set of spreadsheets. See emergency management.
Questions
What are the three EOC activation levels?
Under NIMS (third edition, 2017): Level 3, Normal Operations/Steady State; Level 2, Enhanced Steady-State/Partial Activation; and Level 1, Full Activation.
Is EOC activation level 1 the highest?
Under the NIMS convention, yes. NIMS states that when numbers are used, descending numbers should mean higher levels of activation, so full activation is Level 1. Some jurisdictions have used the reverse, so confirm the local definition.
What is a Level 2 EOC activation?
Enhanced Steady-State/Partial Activation: certain EOC team members or organizations are activated to monitor a credible threat, risk or hazard, or to support the response to a new and potentially evolving incident.
What triggers EOC activation?
NIMS lists triggers including incidents involving more than one jurisdiction or multiple agencies, an Incident Commander's warning that an incident could expand rapidly, a past similar incident that led to activation, direction from the EOC director or an elected or appointed official, an imminent incident, threshold events in the emergency operations plan, and anticipated significant impacts to the population.
Can an EOC activation be virtual?
Yes. NIMS notes that any activation level can involve both in-person and off-site personnel coordinating virtually, and that EOCs may be fixed locations, temporary facilities or virtual structures.
Who decides to activate or deactivate the EOC?
The EOC director or the official named in the emergency operations plan, based on the triggers the plan defines. Deactivation happens when the incident no longer needs the EOC's support and coordination functions.
Sources
- National Incident Management System, Third Edition (October 2017), Table 2: EOC Activation Levels FEMA
- IS-700.b: EOC Activation Levels FEMA Emergency Management Institute
- IS-700.b Lesson 5: Emergency Operations Centers FEMA Emergency Management Institute
- State EOC changes the way it does activation levels Washington Military Department
- EOC Quick Reference Guide FEMA