ELARCHON Request a briefing

FEMA Public Assistance

FEMA Public Assistance alternative procedures (Section 428)

Section 428 lets an applicant take a fixed grant based on an agreed estimate instead of reimbursement of actual costs. It trades cost risk for speed and flexibility, and it suits some projects much better than others.

Updated November 21, 2026 · Reviewed against 5 official and primary sources · Editorial standards

FEMA Public Assistance alternative procedures, authorized by Stafford Act section 428 (42 U.S.C. 5189f), let an applicant receive a fixed grant based on an agreed estimate for permanent work or debris removal, instead of reimbursement of actual costs. The applicant keeps flexibility over how the work is done and may keep underruns for approved purposes, but it is responsible for any costs above the estimate.

Section 428 was added to the Stafford Act by the Sandy Recovery Improvement Act of 2013 to speed up FEMA Public Assistance and reduce administrative cost. It applies to major disasters and emergencies declared on or after January 29, 2013, and participation is always the applicant's choice (42 U.S.C. 5189f(a), (d)).

The four goals in the statute

The alternative procedures must further the goals of (5189f(c)):

Permanent work under Section 428

For repair, restoration and replacement under section 406, the statute requires the procedures to include (5189f(e)(1)):

FeatureWhat it means for the applicant
Fixed estimatesThe grant is based on the agreed estimate. The applicant pays any actual costs above it.
In-lieu contributionThe applicant may elect to receive the estimated cost of repair or replacement, plus management expenses, without reduction.
ConsolidationFEMA may consolidate an applicant's facilities into a single project based on the estimates.
Use of underrunsIf actual costs are lower, FEMA may let the applicant use excess funds for cost-effective risk reduction or to improve future Public Assistance operations or planning.
Expert panelFor projects with an estimated federal share of at least $5,000,000, an independent expert panel is available at the applicant's request to validate the estimate.
Certified cost estimatesFEMA must consider properly certified estimates by mutually agreed licensed engineers; once accepted, they are presumed reasonable absent fraud.

Debris removal under Section 428

For debris removal, the procedures include (5189f(e)(2)):

The specific sliding-scale periods and percentages are set in FEMA guidance for each declaration. Confirm them with your state before deciding. See debris removal.

When Section 428 makes sense

Good fitPoor fit
Well-defined damage with reliable engineering estimatesDamage that is hard to measure until work starts, such as underground utilities
An applicant wants to rebuild differently or consolidate facilitiesAn applicant cannot absorb overruns
Strong in-house project and cost managementVolatile construction prices or long procurement timelines
Large debris volumes an applicant can clear quicklyDebris operations with uncertain access or disposal capacity

Questions to answer before electing

  1. How confident is the estimate? Who prepared it, on what investigation, with what contingency?
  2. What is the overrun exposure? Model the cost if prices or scope move.
  3. What would you do with an underrun? The permitted uses are limited to risk reduction and Public Assistance improvements.
  4. Is the deadline realistic? Section 428 projects carry their own timelines; check the current FEMA guide.
  5. Is the decision documented? Record who decided, on what analysis, and when.

FEMA has issued several guides for the alternative procedures since 2013, and earlier pilot guides have been superseded. Use the current Public Assistance Program and Policy Guide and FEMA's current Section 428 guidance for your declaration.

How Elarchon helps

Section 428 decisions depend on knowing your facilities and your costs. Elarchon keeps damage, asset history and the cost of past repairs by facility, so applicants can test an estimate against their own records before electing a fixed grant. Elarchon is not affiliated with FEMA and does not provide financial or legal advice.

Questions

What are FEMA Public Assistance alternative procedures?

Procedures adopted under Stafford Act section 428 (42 U.S.C. 5189f) that let FEMA make Public Assistance grants for permanent work and debris removal on the basis of fixed estimates rather than actual costs, with incentives for timely, cost-effective completion.

Who can use Section 428?

Participation is at the election of the state, tribal or local government or private nonprofit applicant, and FEMA may not make other assistance conditional on participating (42 U.S.C. 5189f(d)). It applies to major disasters and emergencies declared on or after January 29, 2013.

What happens if the project costs more than the fixed estimate?

The applicant agrees to be responsible for actual costs that exceed the estimate (42 U.S.C. 5189f(e)(1)(A)). That is the main risk of the alternative procedures.

What if the project costs less?

FEMA may allow the applicant to use all or part of the excess funds for cost-effective activities that reduce future disaster risk or improve future Public Assistance operations or planning (42 U.S.C. 5189f(e)(1)(D)).

How does the debris removal sliding scale work?

For debris removal under section 428, the federal share can be set on a sliding scale based on how long removal takes, rewarding faster completion. The current percentages and time periods are set in FEMA guidance for each declaration; check the Public Assistance Program and Policy Guide and your state.

Sources

  1. 42 U.S.C. 5189f: Public assistance program alternative procedures (section 428) Legal Information Institute
  2. 42 U.S.C. 5172: Repair, restoration and replacement of damaged facilities (section 406) Legal Information Institute
  3. 42 U.S.C. 5173: Debris removal (section 407) Legal Information Institute
  4. Public Assistance Program and Policy Guide, Version 5.0 (amended) FEMA
  5. Public Assistance Alternative Procedures Pilot Program Guide for Permanent Work (2013, superseded) FEMA

Request a briefing

See Elarchon configured for your jurisdiction.

Briefings are prepared around your departments, incident types and reporting obligations.

Request a briefing