FEMA Public Assistance has seven categories of work. Emergency work is Category A (debris removal) and Category B (emergency protective measures). Permanent work is Category C (roads and bridges), D (water control facilities), E (public buildings and contents), F (public utilities) and G (parks, recreational and other facilities).
Emergency work must generally be completed within 6 months of the declaration and permanent work within 18 months, under 44 CFR 206.204.
The seven categories at a glance
| Category | Type | Typical work | Completion deadline |
|---|---|---|---|
| A. Debris removal | Emergency | Clearing, removal and disposal of disaster debris from public rights-of-way and property where it poses a threat | 6 months |
| B. Emergency protective measures | Emergency | Search and rescue, emergency medical care, sheltering, road closures and barricades, sandbagging, EOC operations, emergency repairs to prevent further damage | 6 months |
| C. Roads and bridges | Permanent | Road surfaces, bases, shoulders, culverts, low water crossings, bridges, signs and signals | 18 months |
| D. Water control facilities | Permanent | Dams, reservoirs, levees, drainage channels, irrigation and pumping facilities | 18 months |
| E. Public buildings and contents | Permanent | Buildings, contents, equipment and vehicles, including fire stations and their apparatus | 18 months |
| F. Public utilities | Permanent | Water treatment and distribution, wastewater, power generation and distribution, communications | 18 months |
| G. Parks, recreational and other facilities | Permanent | Parks, playgrounds, pools, piers, boat ramps and other facilities not covered above | 18 months |
Category names follow FEMA's Public Assistance process page and fact sheet. Examples are illustrative. Eligibility of a specific item is decided under the Public Assistance Program and Policy Guide. Deadlines run from the declaration date and can be extended by the recipient for documented reasons.
Emergency work: Categories A and B
44 CFR 206.201 defines emergency work as work that must be done immediately to save lives, protect improved property and public health and safety, or avert or lessen the threat of a major disaster.
Category A: debris removal
Debris removal is often the largest early cost for public works departments and the one most often handled by a mix of force account crews, contractors and mutual aid. What usually needs to be shown:
- Where debris was collected and that it was a threat to public health, safety or improved property.
- Quantities, by load and by type, with collection and disposal sites.
- Labor and equipment hours by crew and site, or contract invoices with monitoring records.
- Disposal fees and the site permits that applied.
Category B: emergency protective measures
Category B covers the work most fire, EMS, law enforcement and emergency management agencies do during the incident itself: rescue, evacuation, emergency medical care, security, traffic control, emergency operations center staffing, sheltering and temporary measures to protect property. Two points matter for documentation:
- Labor rules differ. Under 44 CFR 206.228(a)(2), straight-time salaries of permanent employees are not eligible for emergency protective measures, with limited exceptions. Hours need to show regular and overtime separately.
- The threat has to be on the record. Each measure should show the immediate threat it addressed, where and when.
Permanent work: Categories C through G
Permanent work restores a damaged facility on the basis of its pre-disaster design and current applicable codes and standards (44 CFR 206.201). It is planned, estimated and often contracted, so the records look different from emergency work:
- Evidence of pre-disaster condition and maintenance, such as inspection records, work orders and photos.
- Damage descriptions with location, dimensions and photos, captured during the damage inventory.
- The codes and standards that apply, and their adoption date.
- Scope, cost estimate, procurement records and, for large projects, actual costs at closeout.
- Insurance coverage and proceeds, which reduce eligible costs.
Maintenance records created before the disaster are often the deciding evidence for permanent work. An asset history kept in the same system as the response makes them easy to produce.
Why every record should carry a category
FEMA develops projects by category and site, and the rules for labor, deadlines and documentation change between categories. A crew that clears a road, closes it to traffic and starts a culvert repair in a single shift has worked in Categories A, B and C. If the timesheet only says "storm response, 12 hours", someone has to reconstruct the split later, and the hours that cannot be supported are lost.
Recording the category, site and task with each entry from the first shift avoids that reconstruction.
How Elarchon applies categories
In Elarchon, labor, equipment and materials captured during an incident are tied to the dates, sites and work categories they belong to, so emergency and permanent work stay separate from the start. Damage Assessment records feed the damage inventory, and the asset history kept by public works and utilities is available when FEMA asks for pre-disaster condition. Elarchon does not determine eligibility; FEMA does.
Questions
What are the FEMA Public Assistance categories?
Category A is debris removal and Category B is emergency protective measures (together, emergency work). Category C is roads and bridges, D is water control facilities, E is public buildings and contents, F is public utilities and G is parks, recreational and other facilities (together, permanent work).
What is the difference between emergency work and permanent work?
Emergency work is work that must be done immediately to save lives, protect improved property and public health and safety, or lessen the threat of a major disaster. Permanent work restores a damaged facility based on its pre-disaster design and current applicable standards. Both definitions are in 44 CFR 206.201.
How long do we have to complete each category of work?
Under 44 CFR 206.204, debris clearance and emergency work must be completed within 6 months of the declaration and permanent work within 18 months. The recipient can extend those deadlines by up to 6 more months for emergency work and up to 30 more months for permanent work, project by project, for circumstances beyond the applicant's control.
Is regular-time labor eligible for every category?
No. 44 CFR 206.228(a)(2) makes straight-time salaries of permanent employees eligible for permanent work but not for emergency protective measures, with limited exceptions. Recording labor by category keeps those hours separate.
Which category covers emergency services overtime during a storm?
Response activities that protect lives and property, such as search and rescue, emergency medical care, road closures, sandbagging and emergency operations center staffing, are emergency protective measures, Category B. The Public Assistance Program and Policy Guide sets out what is eligible within Category B.
Sources
- Process of Public Assistance Grants FEMA
- Public Assistance Fact Sheet FEMA
- Public Assistance Program and Policy Guide, Version 5.0 (amended) FEMA
- 44 CFR 206.201: Definitions eCFR
- 44 CFR 206.204: Project performance eCFR
- 44 CFR 206.228: Allowable costs eCFR
- Public Assistance Project Templates and Forms FEMA