A sole source purchase skips competition, so it needs a written justification. For federally funded purchases, 2 CFR 200.320(c) allows noncompetitive procurement in only five circumstances.

Updated November 21, 2026 · Reviewed against 7 official and primary sources · Editorial standards

A sole source justification is the written record of why a purchase was made from one source without competition. For purchases with federal funds, 2 CFR 200.320(c) permits noncompetitive procurement only when the amount is within the micro-purchase threshold, only one source can fulfill the need, an exigency or emergency will not permit delay, the awarding agency approves in writing, or competition is inadequate after soliciting several sources. The file must also show the price is fair and reasonable.

The five permitted circumstances

2 CFR 200.320(c) states that the noncompetitive method may only be used if one of these circumstances applies:

CircumstanceWhat you must be able to show
1. Micro-purchaseThe aggregate amount does not exceed the micro-purchase threshold, and the price is reasonable.
2. Single sourceMarket research showing the requirement can be fulfilled only by one source.
3. Public exigency or emergencyThe urgency will not permit the delay of public notice of a competitive solicitation; the period of use is limited to the exigency.
4. Written approvalYou requested, in writing, to use a noncompetitive method, and the Federal agency or pass-through entity approved in writing.
5. Inadequate competitionYou solicited several sources and competition was determined inadequate.

State and local rules may be stricter and may require their own approvals. For the full set of methods, see how to buy government software; for Elarchon's details, government buyers.

Sole source justification template

Use one justification per purchase. FEMA's procurement guidance and PDAT field manual suggest similar elements.

  1. Purchase. Description of the goods or services, quantity, estimated amount, funding source and award or project number.
  2. Circumstance. Which of the five 200.320(c) circumstances applies, cited.
  3. Need. What the agency must accomplish and by when, stated as the requirement, not the product.
  4. Market research. Sources contacted or reviewed, dates, and why each cannot meet the requirement. For an emergency, why there is no time to compete.
  5. Unique capability. For a single source: the specific capability, compatibility or right that only this source has (for example, proprietary integration with an existing system, or exclusive rights).
  6. Price. The independent estimate and the cost or price analysis showing the price is fair and reasonable (200.324), and that the contract is not cost-plus-a-percentage-of-cost.
  7. Responsibility and conflicts. The contractor is responsible (200.318(h)) and not excluded in SAM.gov; disclosure of any known conflicts of interest.
  8. Duration. For an exigency, the period covered and the plan to compete the requirement afterward.
  9. Approvals. Names, titles, dates; written approval from the awarding agency where circumstance 4 applies.

What does not justify a sole source

Emergencies and FEMA funds

After a disaster, many agencies rely on the exigency or emergency circumstance. FEMA does not require prior approval to use it, but its exigency and emergency fact sheet expects the entity to document and justify its use, include the required contract clauses, award to a responsible contractor, complete a cost or price analysis, avoid cost-plus-percentage-of-cost contracts, and limit the use to the actual exigency or emergency period. Keep the justification with the project records for at least the period in 2 CFR 200.334. See FEMA procurement under grants.

This guide explains the federal standard. Your state and local procurement rules, and your legal counsel, govern your agency's decisions.

Questions

What is a sole source justification?

A written explanation of why a purchase is being made from one source without competition, which circumstance permits it, and how the agency determined the price is fair and reasonable. It is kept in the procurement file.

When is sole source procurement allowed under 2 CFR 200?

Under 2 CFR 200.320(c), only if the amount does not exceed the micro-purchase threshold; the item or service is available only from a single source; a public exigency or emergency will not permit the delay of public notice; the Federal agency or pass-through entity approves in writing on request; or competition is determined inadequate after soliciting several sources.

What should a sole source justification include?

The circumstance that applies, a description of the goods or services and estimated amount, the market research done to confirm no other source can meet the need, why competition is not feasible, how the price was determined fair and reasonable, any known conflicts of interest, and approvals.

Does a sole source purchase still need a price analysis?

Above the simplified acquisition threshold, yes. 2 CFR 200.324 requires a cost or price analysis for every procurement transaction above that threshold, starting with an independent estimate.

Can we sole source during a disaster?

When a public exigency or emergency will not permit the delay of a competitive solicitation, 200.320(c)(3) allows noncompetitive procurement. FEMA expects the justification to be documented, the contract to meet the other federal requirements, and the use to last only as long as the exigency or emergency.

Is 'only vendor we know' a valid sole source reason?

No. Single-source justification requires market research showing that only one source can meet the requirement, not that the agency is familiar with one vendor or prefers its product.

Sources

  1. 2 CFR 200.320: Procurement methods eCFR
  2. 2 CFR 200.318: General procurement standards eCFR
  3. 2 CFR 200.324: Contract cost and price eCFR
  4. 2 CFR 200.334: Record retention requirements eCFR
  5. Purchasing under a FEMA award FEMA
  6. Procurement under grants: exigency or emergency circumstances (FY 2025 fact sheet) FEMA
  7. Procurement Disaster Assistance Team (PDAT) field manual FEMA

Request a briefing

See Elarchon configured for your jurisdiction.

Briefings are prepared around your departments, incident types and reporting obligations.

Request a briefing