Contract costs are the most common source of questioned costs in Public Assistance. The rules are in 2 CFR 200.317–200.327, and they apply the moment federal funds may pay for a contract.

Updated November 21, 2026 · Reviewed against 9 official and primary sources · Editorial standards

FEMA procurement under grants means following the federal procurement standards in 2 CFR 200.317–200.327 for any contract paid with Public Assistance funds. Local governments must have documented procurement procedures, avoid conflicts of interest, provide full and open competition, use the procurement method that fits the contract value, perform cost or price analysis, and include the Appendix II contract clauses. Noncompetitive contracts are allowed only in the limited circumstances in 2 CFR 200.320(c).

Procurement is the most common reason contract costs are questioned or disallowed in FEMA Public Assistance. The rules are not FEMA-specific: they are the Uniform Guidance procurement standards that apply to every federal award. FEMA's Procurement Disaster Assistance Team publishes field manuals, checklists and training in its procurement resource library.

Which rules apply to you

2 CFR 200.317 splits applicants into two groups:

ApplicantRules
States and Indian tribesTheir own procurement policies, plus 200.321 (small, minority and women's businesses), 200.322 (domestic preferences), 200.323 (bonding) and 200.327 (contract provisions)
Everyone else: cities, counties, special districts, subrecipients of a state or tribe, private nonprofitsAll of 200.318 through 200.327, and any stricter state or local requirements

General standards (2 CFR 200.318)

Competition (2 CFR 200.319)

All procurement must provide full and open competition. Contractors that draft specifications or statements of work must be excluded from competing on them. 200.319(c) lists practices that restrict competition, including unreasonable qualification requirements, unnecessary experience or excessive bonding, noncompetitive contracts to consultants on retainer, organizational conflicts of interest, and specifying a brand name without allowing "or equal".

Procurement methods by contract value (2 CFR 200.320)

MethodWhen it appliesWhat it requires
Micro-purchaseAt or below your micro-purchase thresholdNo quotes needed if you consider the price reasonable and document why; distribute among qualified suppliers where practicable
Simplified acquisition (small purchase)Above the micro-purchase threshold, not above your simplified acquisition thresholdPrice or rate quotations from an adequate number of qualified sources
Sealed bidsAbove the simplified acquisition threshold; preferred for constructionPublic solicitation, firm fixed price, award to the lowest responsive, responsible bidder
ProposalsAbove the simplified acquisition threshold when sealed bids are not appropriatePublic notice, written evaluation method, award to the most advantageous proposal; qualifications-only selection for architectural and engineering services
NoncompetitiveOnly in the circumstances listed in 200.320(c)Written justification; cost or price analysis

The federal thresholds are the ones in the Federal Acquisition Regulation. You may adopt lower thresholds. You may self-certify a micro-purchase threshold up to $50,000 each year if you document one of the criteria in 200.320(a)(1)(iv) (low-risk auditee status, an annual internal risk assessment, or, for public institutions, consistency with state law). A threshold above $50,000 requires approval from your cognizant agency for indirect costs.

Emergency and exigency contracting

2 CFR 200.320(c) allows noncompetitive procurement only when:

  1. the purchase is a micro-purchase;
  2. the item or service is available only from a single source;
  3. a public exigency or emergency will not permit the delay of public notice of a competitive solicitation;
  4. FEMA or the pass-through entity approves a written request; or
  5. competition is determined inadequate after soliciting several sources.

The exigency exception is time-limited. Document what the emergency was, why competition was impossible, and when normal procurement resumed. Compete follow-on work as soon as the exigency ends. See sole source justification.

Cost and price (2 CFR 200.324)

For every procurement above the simplified acquisition threshold, including contract modifications, perform a cost or price analysis, starting with independent estimates before receiving bids or proposals. Cost-plus-a-percentage-of-cost and percentage-of-construction-cost contracts are prohibited (200.324(c)).

Procurement checklist for a disaster contract

How Elarchon helps

Elarchon's Procurement and FEMA Public Assistance applications keep contract records, purchase orders and invoices on the same record as the work they paid for, by site and category of work. When a reviewer asks how a contractor was selected and what it did, the procurement file and the field record are in one place. Elarchon does not provide legal advice; consult your procurement counsel and your state.

Questions

Which procurement rules apply to FEMA Public Assistance?

The federal procurement standards at 2 CFR 200.317–200.327. States and tribes follow their own procurement policies plus 200.321, 200.322, 200.323 and 200.327. All other recipients and subrecipients, including local governments, follow 200.318 through 200.327, together with any stricter state or local rules.

What is the FEMA micro-purchase threshold?

Under 2 CFR 200.320(a)(1), the federal micro-purchase threshold is the one set in the Federal Acquisition Regulation. A recipient or subrecipient may self-certify a higher threshold up to $50,000 annually if it meets the documented criteria; anything above $50,000 needs cognizant agency approval. Your own policy and state law may set a lower figure.

Can we use emergency or sole-source contracts after a disaster?

Only when one of the circumstances in 2 CFR 200.320(c) applies, such as a public exigency or emergency that will not permit the delay of a competitive solicitation. Document the exigency, limit the contract to the period it lasts, and compete the work as soon as possible.

Are time-and-materials contracts allowed?

Only after a determination that no other contract type is suitable, and only with a ceiling price the contractor exceeds at its own risk and a high degree of oversight (2 CFR 200.318(j)).

Are cost-plus-percentage-of-cost contracts allowed?

No. 2 CFR 200.324(c) prohibits the cost-plus-a-percentage-of-cost and percentage-of-construction-cost methods of contracting.

What contract clauses are required?

The applicable provisions in Appendix II to 2 CFR part 200, as required by 200.327, such as remedies, termination, equal opportunity, Davis-Bacon where applicable, debarment and suspension, and Byrd anti-lobbying.

Sources

  1. 2 CFR 200.317: Procurements by States and Indian Tribes eCFR
  2. 2 CFR 200.318: General procurement standards eCFR
  3. 2 CFR 200.319: Competition eCFR
  4. 2 CFR 200.320: Procurement methods eCFR
  5. 2 CFR 200.321: Contracting with small, minority and women's businesses eCFR
  6. 2 CFR 200.324: Contract cost and price eCFR
  7. Appendix II to 2 CFR Part 200: Contract provisions eCFR
  8. Resource Library: Purchasing Under a FEMA Award FEMA
  9. Public Assistance Program and Policy Guide, Version 5.0 (amended) FEMA