A FEMA Public Assistance documentation checklist covers six groups of records for every project: the declaration and applicant records, force account labor (timesheets and payroll), force account equipment (usage logs and rates), materials (invoices and use), contracts (procurement and payment records) and the work itself (locations, photos, damage descriptions), all retained under 2 CFR 200.334. The checklist below can be copied for each project.
How to use this checklist
Start a copy for each project or work site at the beginning of the event, not after it. Assign an owner for each section. Tick items as records are filed, and note where each is stored. The requirements come from FEMA's Public Assistance Program and Policy Guide (PAPPG) Version 5.0, the regulations in 44 CFR Part 206 and the federal grant rules in 2 CFR Part 200. For context, see the FEMA Public Assistance guide.
Project header
| Disaster number and declaration date | |
| Applicant name and PA ID | |
| Project / site name and location | |
| Category of work (A–G) | |
| Period of work | |
| Documentation owner |
1. Applicant and declaration records
- ☐ Request for Public Assistance submitted, with date. See Request for Public Assistance.
- ☐ Applicant briefing attendance and recipient (state) contacts.
- ☐ Declarations and emergency orders issued by the jurisdiction.
- ☐ Authorized agent designation.
- ☐ Pre-disaster policies in effect: pay and overtime policy, equipment rate policy, procurement policy, mutual aid agreements.
2. Force account labor
- ☐ Timesheets or daily logs for each employee: dates, hours, work performed, location.
- ☐ Payroll records showing regular and overtime pay rates and hours paid.
- ☐ Fringe benefit rate calculation.
- ☐ Pay policy in effect before the disaster (overtime, call-back, standby).
- ☐ Force Account Labor Summary Record or equivalent summary. See force account summary forms.
3. Force account equipment
- ☐ Equipment usage logs: equipment ID, operator, dates, hours operated, location, work performed.
- ☐ Rate source for each item: FEMA Schedule of Equipment Rates for the applicable period, or approved local or state rates.
- ☐ Equipment description matching the rate schedule (type, size, capacity).
- ☐ Force Account Equipment Summary Record or equivalent.
- ☐ Operator hours recorded separately as labor.
4. Materials and supplies
- ☐ Invoices and receipts for purchased materials.
- ☐ Records of materials taken from stock, with the stock price basis.
- ☐ Where and when materials were used.
- ☐ Materials Summary Record or equivalent.
5. Contracts
- ☐ Procurement method used and justification, consistent with 2 CFR 200.318–200.327 and state and local rules. See procurement under grants.
- ☐ Solicitation, advertisement or request for quotes.
- ☐ Bids or quotes received and the evaluation.
- ☐ Cost or price analysis where required.
- ☐ Suspension and debarment check of the contractor (2 CFR 200.214; SAM.gov).
- ☐ Executed contract with required federal clauses.
- ☐ Contractor invoices, proof of payment and monitoring records (for example, debris monitoring tickets).
- ☐ For any noncompetitive (emergency or exigency) procurement: written justification and its duration.
6. Mutual aid
- ☐ Mutual aid agreement (written, or documented verbal agreement) in effect. See the mutual aid agreement template.
- ☐ Request for assistance and acceptance, with dates.
- ☐ Provider's labor, equipment and materials records and invoices.
- ☐ Proof of payment to the provider, where applicable.
7. The work and the damage
- ☐ Site locations (address or GPS coordinates).
- ☐ Dated photographs before, during and after work.
- ☐ Description of damage and of work performed, by site.
- ☐ Evidence of the facility's pre-disaster condition and maintenance, for permanent work.
- ☐ Insurance policies and claims for damaged facilities.
- ☐ Environmental and historic preservation records, where applicable.
- ☐ Donated resources (volunteer hours, donated equipment or materials), if claimed as credit.
8. Retention
- ☐ Records retained for the period required by 2 CFR 200.334 (generally three years from submission of the final expenditure report, longer where an audit, litigation or claim is unresolved) and by state and local schedules, whichever is longer.
- ☐ Storage location documented; records retrievable by project.
Why documentation fails
The most common problems are hours that do not reconcile between timesheets and payroll, equipment hours recorded as time on site rather than time operated, materials that cannot be tied to a site, and contracts procured without the required method or documentation. Each is easier to prevent during the event than to reconstruct afterwards. See force account labor and equipment.
Capturing it during the event
In Elarchon, labor, equipment and materials are recorded during the work and tied to the dates, sites and categories of work they belong to, alongside mutual aid hours and damage assessments, so the summaries draw on records created at the time. Elarchon is not affiliated with FEMA and does not determine eligibility or guarantee reimbursement.
Questions
What documentation does FEMA require for Public Assistance?
Documentation that supports each cost and ties it to eligible work: who did the work and when (timesheets, payroll), what equipment was used and for how long, what materials were bought and used, how contracts were procured and paid, where the work was done, and photos and descriptions of damage and repairs. The PAPPG sets the program's requirements.
How long must FEMA Public Assistance records be kept?
Under 2 CFR 200.334, financial records, supporting documents and other records pertinent to a federal award are generally retained for three years from the date of submission of the final expenditure report, with exceptions such as unresolved audits or litigation. State and local schedules may require longer.
What contracting documents does FEMA review?
Evidence that procurement followed 2 CFR 200.318 to 200.327 and state and local rules: the procurement method, solicitation, bids or quotes received, cost or price analysis where required, the selection, the executed contract with required clauses, debarment checks and invoices.
Can I use my own forms instead of FEMA's summary records?
FEMA publishes force account labor, equipment and materials summary record templates. Applicants may summarize costs in other formats if they capture the same information, but must keep the underlying source documents.
Does this checklist guarantee reimbursement?
No. FEMA determines eligibility. Complete documentation supports a claim; it does not guarantee one.
Sources
- Public Assistance Program and Policy Guide, Version 5.0 Federal Register
- Public Assistance templates and forms FEMA
- Schedule of Equipment Rates FEMA
- 44 CFR 206.228 Allowable costs eCFR
- 2 CFR 200.318 General procurement standards eCFR
- 2 CFR 200.214 Suspension and debarment eCFR
- 2 CFR 200.334 Record retention requirements eCFR
- NIMS Guideline for Mutual Aid FEMA