A lift station inspection checklist records, on each visit, the wet well level and condition, pump run hours, starts and amperage, level control and alarm function, telemetry, standby generator and transfer switch status, valves, odor control and security, plus any work performed. Daily or weekly checks catch failures early; monthly and annual tasks keep equipment within manufacturer guidance.
How to use this checklist
Adapt frequencies to each station's size, criticality and whether it has remote monitoring, and to your NPDES permit and state requirements. Record readings, not just ticks: trends in run hours, starts and amperage show a pump wearing before it fails. Lift station failures are a common cause of sanitary sewer overflows; see the sanitary sewer overflow guide for reporting. Manufacturer operation and maintenance manuals govern equipment-specific tasks.
Visit header
| Station name / ID | |
| Date and time in / out | |
| Operator(s) | |
| Weather / conditions | |
| Reason for visit (routine / alarm / complaint / other) |
Routine visit (daily or weekly)
Site and security
- ☐ Fence, gates, locks and hatches secure; no signs of entry or vandalism.
- ☐ Site clean; no evidence of overflow or bypass.
- ☐ Lighting working.
Wet well
- ☐ Level within normal operating range; record level.
- ☐ Grease, rags or debris buildup noted.
- ☐ Odor and hydrogen sulfide conditions noted (do not enter without confined space procedures).
Pumps
| Reading | Pump 1 | Pump 2 | Pump 3 |
|---|---|---|---|
| Run hours (meter) | |||
| Starts (counter) | |||
| Amperage (each phase) | |||
| Discharge pressure | |||
| Unusual noise / vibration / heat | |||
| Alternation working |
Controls, alarms and telemetry
- ☐ Control panel: no fault lights; record any alarms in the history.
- ☐ Level controls (floats or transducer) operating; pumps start and stop at set points.
- ☐ High-level alarm tested or verified per schedule.
- ☐ Telemetry/SCADA communicating; readings match local readings.
Standby power
- ☐ Generator: fuel level, battery, block heater, no leaks; record hours.
- ☐ Automatic transfer switch in auto position.
Monthly
- ☐ Generator exercise run under load per policy; record duration and any faults.
- ☐ Check valves and isolation valves operate; no leaks at packing or joints.
- ☐ Odor control system (chemical feed, carbon or biofilter) serviced; chemical levels recorded.
- ☐ Clean float switches or verify transducer calibration.
- ☐ Inspect ventilation fans and dehumidifiers in the dry well or control building.
Quarterly to annual
- ☐ Pump drawdown test to estimate pumping rate; compare with design and prior tests.
- ☐ Wet well cleaning as needed.
- ☐ Electrical inspection of panels, motor insulation and connections by qualified personnel.
- ☐ Transfer switch test under load.
- ☐ Review alarm call-out lists and emergency bypass plan.
- ☐ Inspect structure, hatches, ladders and coatings for corrosion.
Work performed and follow-up
| Issue found | Action taken | Work order number | Follow-up needed |
|---|---|---|---|
Operator signature and date.
Keeping the record useful
Inspection logs are most valuable when readings are tracked over time and tied to work orders, so a rising amperage or starts count prompts maintenance before an overflow. They also document the station's condition before a disaster, which matters when damage is claimed under FEMA Public Assistance. In Elarchon, Lift Station Monitoring, Work Orders and the GIS Asset Registry share one record. See water and wastewater.
Questions
What should a lift station inspection include?
Wet well level and condition, pump operation (run hours, starts, amperage, noise and vibration), level controls and floats, alarms and telemetry, standby power and transfer switch, valves and piping, odor control, security, and a log of readings and work performed.
How often should lift stations be inspected?
Frequency depends on the station's size, criticality, telemetry and your permit and state requirements. Stations without remote monitoring are typically visited more often. Set frequencies in your operations and maintenance program and follow manufacturer guidance.
Why do lift station records matter for compliance?
Lift station failures can cause sanitary sewer overflows. Overflow reporting and proper operation and maintenance obligations are set by your NPDES permit and state rules; inspection records show the station was operated and maintained as required.
Should generator tests be part of the lift station checklist?
Yes. Standby power keeps pumps running during outages. Record generator exercise runs, transfer switch tests, fuel level and any faults.
How do lift station inspections connect to disaster reimbursement?
After a declared disaster, records of pre-disaster maintenance and condition help show that damage to the station was caused by the event. FEMA Public Assistance reviews facility condition for permanent work.